Business Bay

Kurdos Investment Reception

Offices · 2,100 sqft · 30 days
×
HomePortfolioOffices › Kurdos Investment Reception
2,100 sqftOffice
30 daysDelivered
ZeroDowntime
94%Staff Satisfaction

The Challenge

Office renovation in Business Bay. Client required brand-compliant fit-out with minimal business disruption.

Our Solution

Phased renovation — night/weekend shifts. Glass partitions, custom joinery reception, branded environment, premium ceiling, IT infrastructure integration.

Planning a kurdos reception? Fixed-price quote in 24 hours

Free site visit for projects over AED 10,000. 3-year warranty on all works.

The Results

Zero business disruption. Completed within schedule. Staff satisfaction survey: 94% positive.

“They renovated our office without a single day of downtime. The phased approach was brilliant.”
— Client · Business Bay
LocationBusiness Bay
CategoryOffices
Area2,100 sqft
Duration30 days
InvestmentAED 320K
I Want This — WhatsApp Free Site Visit →
At a Glance

Kurdos Investment Reception renovation in Business Bay, Dubai, covers 2,100 sqft office fit-out for AED 320K and takes 30 days with zero downtime. First Unicorn Interiors used phased night/weekend shifts for glass partitions, custom joinery, and IT integration, achieving 94% staff satisfaction.

Key facts
  • 2,100 sqft office renovated in Business Bay for AED 320K investment.
  • 30-day timeline using phased night and weekend shifts to avoid disruption.
  • Zero business downtime during the entire renovation process.
  • 94% staff satisfaction from post-project survey.
  • Includes glass partitions, custom reception joinery, and premium ceilings.

Quick answers

What is the cost of office reception renovation in Dubai?
Office reception renovation in Dubai starts at AED 150 per sqft for basic fit-outs, totaling AED 320K for a 2,100 sqft space like Kurdos Investment. This covers custom joinery, glass partitions, and branding. Premium options with IT integration add AED 50K-80K.
How long does an office renovation take in Dubai?
Small office renovations take 2-4 weeks for scopes under 1,000 sqft. Medium projects like 2,100 sqft fit-outs require 30 days with phased scheduling. Large corporate offices over 5,000 sqft span 6-8 weeks including approvals.
What permits are needed for office renovation in Business Bay, Dubai?
Dubai Municipality (DM) issues the Building Permit for structural changes. DEWA approval is required for electrical and plumbing modifications. For Business Bay, Emaar provides the No Objection Certificate (NOC) as the master developer.
What features were included in the Kurdos Investment Reception project?
The project featured glass partitions for open spaces, custom joinery for the reception desk, branded wall environments, premium acoustic ceilings, and full IT infrastructure integration across 2,100 sqft.
What results did the Kurdos office renovation achieve?
The renovation completed in 30 days with zero business disruption. Staff satisfaction reached 94% in surveys. The client praised the phased approach for maintaining operations seamlessly.