15,000 sqft gated mansion required complete interior overhaul. 8 bedrooms, 10 bathrooms, staff quarters, home cinema. Previous contractor abandoned mid-project.
Took over abandoned project, completed structural remediation, full MEP replacement, custom millwork in every room, Calacatta marble bathrooms, Crestron home automation, landscaping with outdoor kitchen.
Rescued from failed contractor. Completed remaining 70% in 140 days. Client saved AED 800K vs starting over. Zero snagging items at handover.