DEWA Approval for Renovation — Process & Requirements
When does your renovation need DEWA approval? This guide covers the full process for electrical load changes, water connections, AC modifications, and more.
When Do You Need DEWA Approval?
DEWA (Dubai Electricity and Water Authority) approval is required whenever your renovation affects the electrical or water infrastructure of your property. Not every renovation needs it — here is when you do.
Electrical Load Changes
Adding new AC units, increasing the number of power circuits, installing high-power appliances (saunas, jacuzzis, commercial kitchens), or upgrading from single-phase to three-phase power. Any renovation that increases your total electrical demand beyond the existing DEWA allocation requires approval.
New Water Connections
Adding bathrooms, outdoor showers, garden irrigation systems, swimming pool water supply, or any new plumbing that requires a separate water connection or increased water flow capacity. Relocating the water meter also requires DEWA approval.
AC Modifications
Changing from split-unit to ducted AC systems, adding AC to previously uncooled spaces (garage conversions, extensions), upgrading compressor sizes, or rerouting refrigerant lines. Like-for-like AC replacement at the same capacity and location does not need approval.
Solar Panel Installation
Installing solar PV systems under DEWA's Shams Dubai programme requires a separate application through DEWA. Your installer must be a DEWA-approved solar contractor. Grid-tied systems require a bidirectional meter installation by DEWA.
EV Charger Installation
EV charger installation requires DEWA approval for the additional electrical load. Level 2 chargers (7-22kW) typically need a dedicated circuit and may require a load increase application. DEWA has specific guidelines for residential EV charging infrastructure.
Smart Home Systems
Comprehensive smart home installations that modify the electrical panel, add dedicated circuits for automation systems, or require coordination with Etisalat/du for network infrastructure. Basic smart switches and WiFi devices do not need DEWA approval.
Step-by-Step DEWA Application Process
The DEWA approval process is straightforward when you have the right documentation. Here are the steps.
Prepare Documents
Gather your existing DEWA account details, property title deed, community developer NOC, contractor trade licence, and MEP drawings. Your electrical consultant prepares load calculations showing existing and proposed electrical demand.
Submit Application
Submit your application through the DEWA website or customer happiness centre. The application must include all technical drawings, load calculations, and supporting documents. Applications can also be submitted through the DEWA smart app.
DEWA Review & Inspection
DEWA engineers review the application and may schedule a site inspection. They verify the existing infrastructure can support the proposed changes. If a transformer upgrade is needed, DEWA will advise on the process and additional costs.
Approval & Payment
Once approved, pay the applicable fees and security deposits. DEWA issues a No Objection Certificate (NOC) which is required for your Dubai Municipality building permit application and your community developer approval.
Post-Work Inspection
After your renovation is complete, DEWA conducts a final inspection to verify the work matches the approved drawings. Once passed, your DEWA account is updated with the new load allocation and any meter changes are finalised.
Required Documents for DEWA Approval
Owner & Property Documents
- Existing DEWA account number and premise number
- Property title deed (copy)
- Owner passport and Emirates ID
- NOC from community developer
- Power of Attorney (if applicable)
Technical Documents
- MEP drawings — electrical single-line diagram
- Electrical load schedule (existing and proposed)
- Plumbing layout drawings (if water work involved)
- Contractor trade licence and DEWA approval card
- Electrical consultant registration with DEWA
- AC schedule showing unit capacities and locations
DEWA Approval Fees and Timelines
| Service | Fee (AED) | Timeline |
|---|---|---|
| Inspection Fee | 200 - 500 | Included in review |
| Minor Modification NOC | 500 - 1,000 | 5-10 working days |
| Load Increase Application | 1,000 - 5,000 | 10-20 working days |
| New Water Connection | 1,500 - 3,000 | 10-15 working days |
| Solar PV Application (Shams Dubai) | Free - 1,000 | 15-30 working days |
| Transformer Upgrade (if required) | 10,000 - 50,000+ | 4-8 weeks |
* Fees are estimates for 2026. Security deposits may apply for load increases and new connections. Confirm current rates at dewa.gov.ae.
Electrical Load for Common Renovations
Understanding electrical load helps you plan your renovation budget. Here are typical load requirements for common renovation elements.
| Renovation Element | Typical Load (kW) | Notes |
|---|---|---|
| Split AC unit (18,000 BTU) | 2.5 - 3.5 | Per unit |
| Ducted AC system | 5 - 15 | Depends on capacity |
| Swimming pool pump + heater | 3 - 8 | Heated pools higher |
| EV charger (Level 2) | 7 - 22 | Dedicated circuit required |
| Sauna / steam room | 6 - 12 | Three-phase often needed |
| Kitchen (commercial grade) | 10 - 25 | Induction + ovens |
| Jacuzzi / hot tub | 3 - 7 | Pump + heater |
* A typical Dubai villa has an allocated load of 50-100 kW. If your renovation pushes beyond this, a load increase application is required.
DEWA vs Etisalat Coordination for Smart Homes
Modern smart home installations often require coordination between DEWA (power) and Etisalat/du (network). Here is how they interact.
DEWA Handles
Electrical panel modifications, dedicated circuits for automation controllers, power supply for motorised blinds/curtains, electrical infrastructure for security systems, EV charging circuits, solar panel grid connection, and any changes to the electrical distribution board.
Etisalat/du Handles
Fibre optic installation and routing, structured cabling for home network, intercom and CCTV network infrastructure, WiFi access point cabling, and any modifications to the telecom entry point. Coordinate with your telecom provider early — lead times can be 2-4 weeks.
Need Help With DEWA Approval?
We handle DEWA applications, load calculations, MEP drawings, and all coordination with your community developer. Our electrical consultants are DEWA-registered and know the process inside out.
